Construction Project and Technology of Light Steel Keel Plasterboard Ceiling

a) Material purchase accessories requirements

1. Light steel skeleton is divided into two types of U-frame and T-frame, and according to the load on the person and not on the person.

2. Light steel skeleton main parts are large, medium and small keel; fittings are hanging pieces, connecting pieces, and hang plugs.

3. Spare Parts: Suspenders, Flower Blue Screws, Shot Screws, Self-Tapping Screws.

4. According to the design instructions can choose to use a variety of cover panels. Aluminum pressure bar or plastic pressure bar, its material species. Specifications. Quality should meet the design requirements.

5. Binder: It should be selected according to the performance of the main material and used for bonding test before use.

(2) The main equipment includes: power saws, toothless saws, nail guns, hand saws, hand planes, pliers, screwdrivers, transfer tools, square feet, steel rulers, and steel level gauges.


Futai dragon integrated ceiling

(iii) Operating conditions

1. During the construction of the structure, it shall be welded in the cast-in-place floor slab or prefabricated floor slab slab. According to the requirements of the radiometer, the prefabricated φ6~φ10 steel reinforced concrete boom shall be embedded. If there is no requirement, the steel beam shall be pre-assembled according to the arrangement position of the large keel. Rod, why the general spacing is 900~1200mm.

2. When the wall of a suspended ceiling room is a brickwork, the anticorrosive wood bricks shall be embedded along the walls and pillars at the elevation of the ceiling, and the distance between the walls shall be 900~1200mm. The columns shall not be buried on either side. Two or more wooden bricks.

3. Install all kinds of pipelines and ventilation ducts in the ceiling, and determine the lighting position, ventilation openings and various exposed hole locations.

4. All kinds of materials are fully equipped.

5. Wall and wet work projects should be completed before the ceiling cover panel is installed.

6. Set up a platform for the roof construction operation platform.

7.Before large-area frame roof construction, the light steel frame ceiling should be used as a model room. The degree of crowning of the ceiling, the construction of lamp channels and vents, and the method of blocking and fixing should be tested and approved before being approved. Area construction.

Ceiling-mounted villa design aisle ceiling paint window room model design

1 23 Next> Total 3 Pages
Page to page
Function assignPage() { var page = $('#page_val').val(); if (/_\d+\.html$/.test(location.href)) { location.href = location.href.replace( /_\d+\.html/, ((page == 1) && 1? '' : '_' + page) + '.html') } else if(/\/\d+\.html$/.test (location.href)) { location.href = location.href.replace(/(\d+)\.html/, ((page == 1) && 1? '$1' :'$1_' + page) + ' .html') } } $(function(){ $('#page_form').submit(function() { assignPage() return false; }) $('#page_btn').click(function(){ assignPage( ); return false; }) }) See full story

Parallel Groove Clamp

Parallel Groove Clamp,Quick Grip Clamps ,Plastic Clamps ,Furniture Clamps

Hardware Accessories Co., Ltd. , http://www.nbhardwares.com